As cold weather gripped the nation and temporarily stalled work in cities across the South in the new year, the Savannah Harbor Expansion Project continued to check items off its to-do list.

Posted in Dissolved oxygen, SHEP | Tagged , , , , , , , , , , | 1 Comment

Wetland acquisition advances SHEP progress

The Savannah Harbor Expansion Project (SHEP) continues to make progress, most recently demonstrated by the completion of another environmental mitigation requirement.

Posted in SHEP | Tagged , , , , , , , , , , , , , , | 3 Comments

SHEP spotlight: DO system

SAVANNAH, Ga. – Contractors with CDM Constructors Inc. are finishing concrete placement for the intake structure on the downriver site of Dissolved Oxygen Injection System. The project is scheduled to be completed by the end of the year. The system … Continue reading

Posted in Dissolved oxygen, Videos | Tagged , , , , , , , , , | Comments Off on SHEP spotlight: DO system

Contractors on pace to finish 5 SHEP-related features in 2017

SAVANNAH, Ga. – To say Spencer Davis has a few irons in the fire is an understatement. As the senior project manager for the Savannah Harbor Expansion Project, or SHEP, Davis manages the multimillion-dollar project that has eight separate environmental … Continue reading

Posted in CSS Georgia, SHEP, Videos | Tagged , , , , , , , , , , | Comments Off on Contractors on pace to finish 5 SHEP-related features in 2017

New arrivals push DO system closer to completion

Workers delivered four Speece cones to the downriver Dissolved Oxygen Injection System site, Dec. 14, 2016. The Speece cones, which are 22 feet tall, 12 feet in diameter at the base, and weigh more than 11 tons, force oxygen into … Continue reading

Posted in Dissolved oxygen, Savannah Harbor, SHEP, Videos | Tagged , , , , , , | Comments Off on New arrivals push DO system closer to completion